Design Partner Program · now accepting five operators for 2027Apply
Sheet A-000 · Site overviewAI infrastructure operations
AI infrastructure analytics for power-constrained data centers

Every megawatt, engineered into compute.

Aidni is the AI infrastructure analytics and operations layer for data centers that are short on power. We model your site as one system, covering power, cooling and compute, plan against the grid capacity you actually have, and give AI agents a safe, two-verb interface to help run it.

Plan · Build · Operate · Prove

One Facility Graph. Four modules. Agents that observe and propose, and people who approve.

Fig. 1 · Facility system modelSchematic · NTS
POWER CHAINCONTROL & EVIDENCETHERMAL CHAINUTILITYStaged feedSUBSTATIONInterconnectSWITCHGEARMV / LVUPSRide-throughPDUBuswayHEAT REJECTDry coolersCLOSED LOOPFacility waterCDUDirect-to-chipCONDUIT AGENTSObserve · Propose → approveLEDGERPUE · WUE · energy / workloadDATA HALL · GPU RACKS
PlanAidni Grid

The utility delivers capacity in stages. Grid computes what each phase can energize after PUE and redundancy, then fits racks and GPUs into that envelope.

Open Aidni Grid →
From substation to rack · one system
Large electrical transformer in a power substation
Power · Utility transformers set the site's ceiling.Stock photo · Unsplash
Industrial pipes and valves of a cooling loop
Thermal · Facility water loops carry heat from chip to sky.Stock photo · Unsplash
Aisle between rows of equipment racks in a data hall
Compute · Dense GPU racks turn megawatts into tokens.Stock photo · Unsplash
Why now · the AI build-out is limited by power delivery, not demand
Up to 12%Share of US electricity data centers may use by 2028, up from 4.4% in 2023Source: LBNL, 2024 US Data Center Energy Usage Report
$30M+Cost of the compute inside, per megawatt — about 3× the buildingSource: Brookfield, 2026 Infrastructure Outlook
842US data centers under construction, alongside 2,104 operatingSource: Aterio, Sep 2026
$6.7TProjected global data center build-out spending by 2030Source: McKinsey & Company, 2025
01 · The constraint

The bottleneck moved from the server to the substation.

Servers keep getting more efficient. Getting power to the site is what now stops a build, and the hardware waiting for that power is the most expensive thing in the building.

Electrical substation with transformers and power lines
Power01

Interconnects arrive in tranches

A campus is designed for its final load but energized in stages. Without a model of the full power chain, headroom and stranded capacity are guesses.

Server rack with status lights in a data hall
Capital02

Idle compute is the costliest asset you own

Compute can exceed $30M per MW and accelerators age out in 24–36 months. Every month a GPU waits for power is useful life it never earns back.

Rows of industrial cooling units on a rooftop
Cooling03

Water is a design decision

Closed-loop systems consume almost no water; evaporative systems consume it continuously. The choice gets made early and gets scrutinized in permitting.

03 · Foundation

The Facility Graph: one model instead of five systems.

Power data lives in EPMS, cooling in the BMS, space in DCIM, workloads in the scheduler and plans in spreadsheets. Aidni connects them read-only into one typed graph, so a single query can trace a GPU job back to the feeder that powers it and the loop that cools it.

  • Read-only connectors by default. Nothing is written back to site systems.
  • Published formulas for every derived number, with an audit trail per metric.
  • Deploy in Aidni cloud, your VPC, or on-premises and air-gapped.
See the architecture →
FIG. 2 · PLATFORM ARCHITECTUREread + proposeread-onlyA-101 · PLANGridPower envelopePhased compute planStranded-MW valueA-102 · BUILDThermalCooling comparisonWater by designLiquid readinessA-103 · OPERATEConduitMCP agent gatewayObserve + ProposeHuman approvalA-104 · PROVELedgerPUE · WUEEnergy / workloadAudit trailFacility GraphOne typed model of every power, thermal and compute asset, and how they connectPOWER CHAINUtility › UPS › PDU › rackTHERMAL CHAINHeat reject › CDU › chipCOMPUTE CHAINRack › GPU › job › tokensEPMSBMSDCIMGPU schedulerUtility dataFire, EPO and safety interlocks sit permanently outside the agent surface.
04 · Agents, safely

Eight operations, or two verbs?

The obvious way to give an AI agent access to a system is to expose every operation an engineer can perform. We expose two. Observe lets an agent discover what exists and what it is doing. Propose lets it draft any change, with risk and rollback, for a person to approve.

Everything else an agent needs is a composition of those two. Our founder argued for this design on MuleSoft's MCP Server at Salesforce, and it shipped. Conduit applies it to the facility.

How Conduit works
Typical agent surfacecreate()read()update()delete()start()stop()configure()schedule()
Conduitobserve()propose()+ human approval in your change process
Steel building frame under construction beside a tower crane
Hundreds of new US data centers are under construction.Stock photo · Unsplash
07 · The future of the data center

Built for the next decade of AI infrastructure.

Demand is set to more than double by 2030, the grid has become the gate, and AI is entering the control room. Founded by Karishma Mandal, Aidni introduces the analytics model, planning method and agent interface that this era needs.

Start here

Bring us one site. We will show you its real capacity.

A six-week Site Assessment maps the power envelope, the cooling design and the compute plan for one facility, delivered by the engineers who build the platform.