Modeled scenario · Aidni planning model · public cost assumptions

The cost of a staged interconnect: a 60 MW reference campus

A reference campus receives 60 MW in two 30 MW tranches. If second-phase GPUs arrive three months before second-phase power, the idle hardware loses about $60M of its useful life.

Key facts
Allocation2 × 30 MW tranches
IT per phase24 MW at PUE 1.25
GPUs per phase13,248 (184 racks × 72)
Compute capital per phase$720M at $30M/MW
Life consumed while idle~$60M over 3 months
What happened

Each 30 MW tranche supports 24 MW of IT load at a design PUE of 1.25: 184 racks at 130 kW, or 13,248 accelerators at 72 per rack. At $30M of compute capital per MW, each phase carries about $720M of hardware.

On a 36-month useful life, that hardware consumes about $20M of value per month whether or not it is powered. A three-month gap between delivery and energization costs roughly $60M. Grid sequences procurement against the energization schedule so the gap is planned out before the purchase order is signed.

Modeled scenario using public cost assumptions. Not a customer engagement.

What it proves for Aidni

Why power-first planning matters: the largest avoidable cost in a staged build is not energy, it is idle compute.